- Petrobrazi Refinery turnaround lasted 6 weeks and required approximately 2 million of worked man-hours
- Operations resumed on schedule following EUR 45 mn modernization and maintenance works
On May 28, operations were resumed right on schedule at Petrobrazi Refinery in Ploiesti, after the 6 weeks planned turnaround. The turnaround consisted in periodical maintenance works, inspections and verifications of refinery facilities, requiring approximately 2 million worked man-hours. The total value of the project, covering investment and costs was around EUR 45 mn.
You can find additional details in the enclosed press release.